We received a resolution to grant planning permission in March 2025 for our application to redevelop Euston Tower into a world-leading science, technology, and innovation building for Camden and the Knowledge Quarter with benefits to Camden and its communities. businesses.
We have recently appointed Keltbray to carry out essential power infrastructure upgrades which includes the construction of a new electrical substation within the existing Regent’s Place basement. To facilitate this, preparatory works will be required in the Regent’s Place Plaza, along its boundary with Euston Road.
From 19 January 2026, hoarding will be installed around the lawn on the southern edge of the plaza and works will commence. Pedestrian access between Euston Road and the plaza will be maintained at all times and retail units within Euston Tower facing the plaza will remain open and trading as usual.
During the early stages of the programme, there will be limited periods of noisier activity associated with the removal of sections of the plaza slab. To minimise disruption to residents and customers, noisy activities will be:
- Limited to morning / evening commuting hours (8:00am-9:30am and 5:00pm-6:00pm) and lunch time (12:00pm-1:00pm)
- Time-limited, lasting approximately 14 days
We anticipate the works will continue until July 2026, but much of this work will be contained within Regent’s Place. Following the works we hope to commence with the redevelopment of Euston Tower itself. Working closely with our contractor to minimise disruption we will ensure that impacts on neighbours, businesses, and public spaces are carefully managed.
We appreciate your understanding and cooperation as we begin this exciting transformation of Euston Tower and the wider campus. If you have any questions, please contact: